![]() |
|||||||||||||||||||||||
|
|
|||||||||||||||||||||||
|
Revised: 1 April 2004 |
|||||||||||||||||||||||
| The Telecommunications Infrastructure Initiative (TII)
is being funded from two sources: the proceeds of
the sale of a bond authorized by the voters of the
State of California under Proposition 1A (Prop 1A)
in 1998 and technology funds held by the
California State University Chancellor's Office in
a central, systemwide account (CO Tech Funds).
These moneys can be used only for the TII
build-out and provisioning of permanent,
State-owned buildings. Development of
communications to temporary building must come
from the University operating budget. The
University must also develop its own funding
mechanism for most of the ongoing refresh and development
costs
after the TII project is completed. |
|||||||||||||||||||||||
| The Telecommunications Infrastructure Initiative
build-out is being treated by the State of
California as a construction project. Such
projects go through four stages. The Chancellors'
Office department for Capital Planning, Design and
Construction (CPDC) describes these phases as
Preliminary Plans ("P"), Working
Drawings ("W"), Construction
("C"), and Equipment ("e").
The project budget is as follows: |
|||||||||||||||||||||||
Details of this budget are as follows: |
|||||||||||||||||||||||
| Preliminary Plans |
|||||||||||||||||||||||
| The Preliminary Plans are the initial
architectural drawings used to scope and develop a
preliminary budget for a project. The budget for
the preliminary planning is $551,000 funded from
the proceeds of the sale of a bond approved by the
voters of the state under Proposition 1A (Prop 1A)
in 1998. |
|||||||||||||||||||||||
| Working Drawings | |||||||||||||||||||||||
| The working drawings build on the Preliminary
drawings by adding sufficient detail to be used as
bid documents for the selection of a Contractor.
For review purposes, working drawings are
developed in completion phases of 50%, 90% and
100%. The budget for working drawings is $406,000,
with $337,000 funded by Prop 1A and the remaining
$69,000 funded by the Chancellor's Office from
technology dollars (CO Tech Funds) that are
included in the budget "compact" with
the Governor. |
|||||||||||||||||||||||
| Construction |
|||||||||||||||||||||||
| Most of the conduit that is required for
interbuilding media is being installed as part of
the Campus Utility Project. The value of this part
of the project is about $1,000,000, with those
costs being absorbed by the Utility Project. This
approach means the campus will not need to be
trenched twice (once for the Utility Project and
once for TII). However, there is some additional
trenching that will be required. The budget for
this part of construction is $93,000 funded by
Prop 1A. |
|||||||||||||||||||||||
| The primary part of construction will be the
build-out of the entry ways (where the
interbuilding media enters a building), spaces
(telecommunications equipment rooms), pathways
(cable trays, risers, etc.), and media (copper,
coax, and fiber). The budget for construction is
$5,161,000, with $4,741,000 funded by Prop 1A. The
remaining amount, $420,000 for intrabuilding
media, will be funded from the CO Tech Funds. A
further $386,000 is budgeted for hazardous
materials removal, funded by Prop 1A. |
|||||||||||||||||||||||
| The project also includes a budget of $204,000 for
architect services during construction, $433,000
for contract management services, and a
contingency of $401,000. Of this total, $889,000
is funded by Prop 1A, and the remaining $149,000
will be funded with CO Tech Funds. |
|||||||||||||||||||||||
| Equipment |
|||||||||||||||||||||||
| The Equipment budget is $1,740,000 funded from the
CO Tech Funds. This amount is to pay for the
electronics (switches, routers, hubs, amplifiers,
firewalls, network operations center, etc.) as
well as design and implementation services from a
systems integrator. The campus will use its
existing data networking equipment as a trade-in. |
|||||||||||||||||||||||
|
Other Required Services |
|||||||||||||||||||||||
| Throughout a large construction project such as
the TII, there are a number of additional services
required, such as fire marshal inspections, plan
checks, testing, and hazardous materials surveying and
monitoring (separate from hazardous material
removal). The project budget for these other
required services is $304,000 funded by Prop 1A. |
|||||||||||||||||||||||
| Refresh |
|||||||||||||||||||||||
| The TII calls for the refresh (scheduled
replacement) of the electronics on a regular cycle
to ensure the network stays state-of-the-art:
typically a three-year cycle for most of the
equipment. The Chancellor's Office intends to
distribute CO Tech Funds to the campus to assist
with the associated costs. However, the amount
allocated will be based on the value of the
electronics installed during the initial project
and this amount will not be increased for either
inflation or expansions of the network. |
|||||||||||||||||||||||
| For example, when the Behavioral and Social
Sciences Building comes on line, the network
infrastructure for the building will be included
in its construction costs and the electronics to
light up the building will be included in what is
called Group II costs as part of its equipment
stage. When it comes time to refresh the
electronics in the BSS Building, the campus will
need to provide its own funds to do so. That means
that over time, the CO Tech Funds will not be
sufficient to pay for a campus-wide refresh. |
|||||||||||||||||||||||
| Telecommunications and Network Services will need
to develop a funding mechanism to paying these
excess costs. One approach would be to allocate a
direct support budget from the University's
general fund. Another approach would be to charge
a connect fee which would pay for the on-going
support and refresh costs of the network. Such a
charge would apply to all connections on the
campus, not just those added after the project
completes – all users should receive equivalent
services for equivalent charges, and the costs
should be considered a campus-wide obligation
where everyone contributes to the solution.
Extensive consultation will be used to develop a
funding mechanism, and a formal proposal will be
submitted through the University Resource Planning
and Budget Committee. |
|||||||||||||||||||||||
|
Caveat |
|||||||||||||||||||||||
| The CO Tech Funds come from general funds in the
Chancellor's Office which are available because
the California State University has a
"compact" with the Governor that the CSU
budget will grow by a known amount each year based
on the CSU's willingness to take additional
students. The compact gives the CSU a secure
budget-planning environment in which it can make
long-term commitments to initiatives because it
knows the funding will be there. With the dot-com
bust, the energy crises, and all the other
pressures on the California economy, it is within
the realm of possibility that the compact might
need to be broken at some point in time and the CO
Tech Funds lost. If that happens before the
completion of Humboldt's project, we may have to
make up for the loss of those Tech Funds in order
to complete the project. |
|||||||||||||||||||||||
| The CO Tech Funds also face a second potential
threat. The Prop 1A funds only cover the TII
project costs for two-thirds of the CSU campuses.
The expectation is that the voters will pass a new
bond measure in 2002/03 to fund the project for
the other one-third. If the bond were not to pass,
it will be only fair for the CSU to fund that
other one-third from some internal source, which
could the CO Tech Funds. |
|||||||||||||||||||||||
| Telecommunications and Network Services has
established an account in which it is holding
funds to equip temporary buildings on the campus
because temporary buildings cannot be equipped
using funding from Prop 1A. If CO Tech Funds are
lost, some of that loss will have to come from the
TNS account, essentially depleting that account,
and the campus still may be required to come up
with additional funds. |
|||||||||||||||||||||||
| | | | | | | | | | | | | | | | |
What's |
| |
Construction |